Road Construction continues on Nordic Drive

 

Shelly Pope

SECON workers continue the demolition of Nordic Drive in order to install new storm drain pipes and structures. Dowl HKM Project Engineer, Matt McGuan says they are planning to have this portion of Nordic Drive paved by July 4.

Dowl HKM and SECON workers continue to make progress on the Petersburg Road Improvement Project down Nordic Drive.

“We have completed the work on Dolphin Street at the PFI loading dock,” Acting Dowl HKM Project Engineer Eric Voorhees said. “We have also completed installing the concrete pavement on Excel Street east and half of Excel Street west.”

The pavement on Nordic Drive has been removed and workers have begun the installation of storm drain structures and piping.

According to SECON Project Superintendent Bryce Iverson, over the next two weeks, storm drain pipe and structures w...