The library landscaping request for proposals is planned for mid-December through January.

The North Harbor project letter of completion was received on Oct. 29 and a final payment was made.

Last week the abutment was poured and Tamico is currently securing the last girders on the Drive Down Facility Approach Dock. Rock-N-Road Construction has trenched the uplands and is working with Petersburg Municipal Power and Light and Bear Electric to install the conduit and parking lot light pole b...